Important Points from IS CODES 456 2000

Dear friends,
      As a civil engineer, we must have knowledge about IS codes and there uses in construction so that we can be more confident and can perform the work easily according to Indian standards and quality.
    So Myself Er. Suleman Ansari trying to give some points that will definitely increase your knowledge and can perform according to that.
      I want to give the information that I have a youtube channel named tech civil world so please visit and search Important points for IS CODE 456 I have explained in proper way.

THE VERY FIRST POINTS

ABOUT CONCRETE

CLAUSE-7.1 PG-17  (IS CODE
 456 2000)

WORKABILITY OF CONCRETE-

(EASE OF PLACING OF 

CONCRETE) 
   
SLUM CONE TEST AND

 CRITERIA OF ACCEPTANCE

The second point is 

Frequency of sampling of 


concrete CUBE- pg.- 29- 15.2.2-

IS CODE 456 -2000

11) for 1 to 5 cum of concrete.:- 1
2) for 6 to 15 cum of concrete.:- 2
3) for 16 to 30 cum of concrete.:- 3
4) for 31 to 50 cum of concrete.:- 4
5) for 51 and above:- 4 + one additional 
three settings for each sample for curing period of 
28 days

MINIMUM CURING PERIOD OF


 CONCRETE 


13.5.1—PG -27-IS 456 2000
1) At least 7 days from the date of placing of concrete.
2) In Case of Portland cement- minimum 10 days when mineral admixture or blended cement is used.
3) At least 10 days in dry and hot weather conditions.
4) minimum days extended to 14 days.
DESHUTTERING PERIOD OF CASTING CONCRETE OF DIFFERENT STRUCTURES
PG NO.   25  Clause-11.3.1 is code 456-
 2000


-------------------------------------------------------

Go for this link for is code 456 2000